Contact Information General Information Number: (415) 473-6907 - Fax: (415) 473-4120 - TDD: (415) 473-6368
3501 Civic Center Drive, 236;
San Rafael, CA 94903-4157 View Map
Monday through Friday, 8:00 a.m. to 4:00 p.m.
Performance Evaluation Guidelines
Introduction
The purpose of these inspections will be to determine,
on an individual basis, whether existing septic systems are functional
and meet minimum standards of performance established by the San Francisco
Regional Water Quality Control Board (RWQCB) and the County of Marin,
Environmental Health Services (EHS). The following performance criteria
are established as minimum requirements:
There is no surfacing effluent at any time.
The effluent is not discharged directly to ground water. This means that
site ground water levels may not rise above 36 inches below the leachfield
lines.
There is always positive flow from the leachfield and from the septic
tank with no backup to the tank or house plumbing during high
groundwater conditions.
There is an adequately sized septic tank for the structure being
served and it must be serviceable - e.g. access riser for
maintenance. The septic tank must be water tight and constructed
of approved materials.
The following sets forth procedures in conducting performance evaluations,
to assure consistency and thoroughness in verifying the functioning
status of existing septic systems.
Inspection Responsibility
The inspections shall be carried-out by a Registered Civil Engineer
or Registered Environmental Health Specialist. The individuals conducting
the field inspection work shall be well-versed in the operation
and maintenance of on-site sewage disposal systems and trained specifically
in the testing and inspection procedures outlined in this document.
Background Data
Prior to conducting the field performance inspection all background
information pertaining to the property and septic system shall be
compiled and reviewed. This should include permit information, site
plan, "As Built" drawings of the septic systems, prior sanitary
survey inspection results, etc.
The site plan must show the location of the septic tank and leachfield,
the location of all buildings, decks, cutbanks, creeks, wells, reserve
or fail-safe area, direction and percentage of slope, or any other
items which may affect the septic system. If a reserve or rail-safe
area is not specified or if any proposed construction encroaches
upon it, a new reserve area must be identified. The evaluation must
address system performance during wet weather conditions as well
as dry weather conditions.
Initially, the inspector should walk the property to confirm the
location of the septic tank, leachfield, and other pertinent features
of the system. In verifying the leachfield location, the length
of each line and the depth of the drainpipe (below ground surface)
shall also be determined for comparison with observed groundwater
conditions. This may require probing with a metal rod or actual
excavation.
The septic tank and disposal field areas should be checked for
any obvious signs of existing system problems such as surfacing
effluent, odors, greywater bypasses, selective fertility (e.g.,
lush vegetation in the leachfield area) or any other condition that
may suggest an existing or impending problem. The inspector should
determine if the system has dual leachfields, and, if so, locate
and check the diversion valve, (a) to see that it is functional;
and (b) to determine which leachfield is in service. All observations
should be noted.
As part of the initial site reconnaissance a hand-augured boring
(3-inch minimum) shall also be made alongside (but not within) the
leachfield area for observation of groundwater conditions. An initial
reading (i.e., depth to groundwater from ground surface) shall be
taken when the boring is made. The boring shall then be left open
for the remainder of the performance inspection so that a final
reading may be taken after the water level has been allowed to stabilize
for about 1-hour. The boring should be backfilled before leaving
the site.
Septic Tank Inspection
After the initial site reconnaissance has been conducted, the detailed
inspection of the system should commence.
Access Risers
First, locate the septic tank and determine if permanent access
risers have been installed on the septic tank. If the tank is equipped
with risers, check their general condition. Ideally, the risers
should be properly grouted to the top of the septic tank to prevent
groundwater and/or surface water intrusion. The lids of the risers
should also be properly sealed to prevent odors and the entry of
insects. (e.g., flies, mosquitoes, etc.). Any observed defects in
the access risers should be noted. If the tank lacks access risers,
this information should be so noted; and the property owner should
be provided information about access risers and shall be required
to install them.
Opening the tank
After inspecting the access risers the septic tank lids should
be carefully removed. Care must be taken if gardens and shrubs are
near to prevent damage and to disturb the yard area as little as
possible. Concrete lids are heavy and may be "cemented" in place
by silt. A steel bar or other suitable tool may be needed to assist
in opening the lids. During the tank inspection process, personnel
should wear protective boots and gloves (neoprene) to guard against
infection from pathogenic organisms.
Structural Condition
Once the tank is open, the inspector should observe and probe the
structural condition of the septic tank to check for any obvious
signs of cracking or other structural defects in the tank. A steel
rod is used to probe the walls and bottom of the tank. Normally,
the tank will not need to be pumped-out to perform this procedure.
The inlet and outlet sanitary "tees" should also be inspected to
assure that they are in satisfactory condition, properly positioned,
and free of scum accumulation, rocks, root matter or other obstructions.
Any problems should be noted and the inspector shall conduct whatever
additional tests or observations necessary to verify the structural
integrity of the septic tank.
Liquid Level
The liquid level in the tank should be measured
with respect to the outlet pipe. In a properly functioning system, the level
in the tank should be even with the invert (i.e., bottom of the outlet pipe
(see
Figure 1). If the liquid level is below the outlet pipe, the tank is leaking.
If the liquid is above the pipe, the leachfield is either flooded or obstructed.
The depth of water above or below the outlet pipe should be measured and noted.
Tank Capacity
The capacity of the septic tank (in gallons) shall be determined
from measurements of the width, length and depth (below outlet pipe)
of the tank. The capacity shall then be compared with the established
water use/wastewater flow rates for the property. A minimum septic
capacity of 3 times the maximum expected daily wastewater flow rate
shall be required for the existing septic tank size to be judged
adequate. If this criteria is not met or there is any uncertainty
regarding compliance, then additional tank capacity is required.
The inspector should then proceed with the hydraulic load test
of the septic tank and disposal field. The test, as described here,
is conducted only for standard gravity-fed leachfields, and does
not apply if the system utilizes a pump. A separate test to be conducted
for pump systems is described in the next section. The hydraulic
load test is conducted by surcharging the septic tank with about
150 gallons of water over a 20-30 minute period; and then observing
the rise of water in the tank and the subsequent draining process.
(Tracer dye may be used to assist in observing leachfield failure).
A garden hose discharging into the outlet side of the tank can be
used to surcharge the tank. The hose outlet should remain well above
the water level in the tank to prevent cross contamination. Before
starting the test, the flow rate from the hose should be determined
(i.e., with 5-gallon bucket and stop watch) to properly gauge the
amount of surcharge water added to the tank. Alternatively, a portable
water meter can be installed between the house faucet and the hose
to directly measure the water volume added.
Test Procedures
The step-by step procedures for the hydraulic load test are then
as follows:
Measure the location of the static water line in the septic
tank (at the outlet side) as an initial reference point.
Begin surcharging the tank with water to start the hydraulic
load test.
Observe any rise in the liquid level at the outlet pipe and
measure the water level at the end of filling. Typically, the
liquid level will rise from 0.5 to 1-inch, at which point the
liquid level should stabilize for the remainder of filling; and
the return to the initial level in a matter of minutes after filling
is stopped.
After the filling cycle is finished, the water level decline
in the septic tank is observed until the initial level is reached;
and the time to achieve this is recorded. If the initial level
is not attained within 30-minutes, the test is terminated and
the final water level is noted.
System Rating
Based upon the water level readings during
the test, a hydraulic performance rating shall be assigned to the system in
accordance with the guidelines provided in Table
1. It should be emphasized that these are guidelines only, and
special circumstances may be caused for modifying the evaluation and rating
of particular systems. A system receiving a "Failed" rating shall require appropriate
upgrading.
Final Leachfield Inspection
At the completion of the hydraulic load test, the drainfield area
and downslope areas should be checked again for indications of surfacing
effluent, wetness, or odors. If any of these conditions exist as
a result of the hydraulic load test, this shall be considered conclusive
evidence of system failure. If the field observations of wetness
are not obviously the result of the hydraulic load test, further
investigation may be necessary to determine if the drainfield is
failing and the cause of the failure. Additional investigative work
may include water quality sampling (for total and fecal coliform,
ammonia and nitrate) or dye testing. The cause of seepage could
be related to gopher holes, site drainage or erosion problems, excessive
water use or simply the age of the disposal system.
For systems equipped with an effluent pump,
the following inspection procedures should be followed. Figure
2 provides a diagram of a typical pump system installation for reference.
General
Remove the pump access cover and basin lid, taking care that no
soil or other material enters the basin. Note any signs of scum
or sludge buildup, indications of previous pump failure (such as
scum line above the high water alarm switch), or evidence of soil
or roots entering the basin. Also, inspect the float controls to
see that they have free movement, and check the electrical junction
box (if located in the basin or access riser) for any obvious signs
of corrosion. If the water level in the basin is normal (i.e., between
the high and low water controls) proceed with testing of the pump
systems.
Pump Test
The pump test is conducted by adding sufficient water to the basin
to activate the pump "on" control and observing the performance
of the system over at least one pumping cycle. The total amount
of water added should be about 150 gallons, to approximate the same
hydraulic loading of the leachfield as for gravity systems. Using
a garden hose, the water may be added to the outlet side of the
septic tank, or directly to the pump basin. If filling the basin
directly, care should be taken to minimize turbulence and disturbance
of sediment or sludge that may have collected in the basin. This
can be best accomplished by directing the stream of water against
the interior side of the chamber, rather than directly toward the
bottom of the pump chamber.
Observe the filling of the basin, and note and measure the point
at which the pump is activated. Immediately stop the filling operation
and observe the pumping cycle until the pump shuts-off. While the
pump is discharging, examine the piping system for any leaks. Even
small leaks could be a forewarning of possible breaks in the pressure
line at some point in the future; and these should be corrected
as soon as possible. Note and measure the depth at which the pump
shuts-off, and calculate the volume of water between the "on" and
"off" measurements. Compare this dose with the design dose volume
specified for the system. If the dose is too high or too low, float
controls should be done by a licensed and properly qualified contractor
(not by the inspector).
The pumping cycle (from "on" to "off") levels should be timed and
the results recorded on the inspection form. Typically, if the pump
is sized and operating properly, pump operation lasts 1-5 minutes
per dose. Pump cycles lasting longer than this may indicate leachfield
clogging and/or pump deficiencies. If this is observed, it should
be noted and further investigation of the pump and leachfield should
be conducted to determine the specific cause.
If during filling of the basin, the pump does not activate when
the water reaches the high liquid level control (i.e., "on" float),
discontinue the pump test. This indicates a pump failure, defective
float switch or wiring problems and will require the repair service
of a competent contractor familiar with these types of systems.
The pump system failure should be noted, communicated immediately
to the resident/owner, and followed-up with a notice requiring prompt
corrective action.
Leachfield Inspection
At the completion of the pump test, the disposal field area shall
be checked for signs of seepage in the same manner as done for gravity-fed
systems following the hydraulic load test.
Clean-up
At the completion of the septic system inspection and testing,
the inspector shall replace all access lids and clean all tools
before leaving the site. All tools, and equipment that come into
contact with wastewater should be cleaned and disinfected with a
1:5 bleach solution; and all contaminated rinse water shall be disposed
of in the septic tank.